Greetings
Miners!
On Monday (13/01/2014) we
released an outline of our set roadmap, today as promised we will be releasing
a timeline with dates on each aspect of the development process. This shows our
commitment to transparency and gives a better idea on what exact stage we are
on at all times. As we go through multiple developmental stages in parallel, we
will be releasing regular detailed updates on our progress. Our next updates
will be consistent developmental updates on what is being worked on and what
has been achieved.
Timeline:
Project
Start: 16/08/13
Project
Finish: 15/07/14
Task
Name |
Duration |
Start |
Finish |
Viper ASIC Miner Project |
238 days |
Tue 16/08/13 |
Tue 15/07/14 |
Scrypt
Core and Chip Architecture |
15 days |
Mon 06/01/14 |
Fri 24/01/14 |
System
Architecture |
5 days |
Mon 06/01/14 |
Fri 10/01/14 |
FPGA
Implementation and Testing |
131 days |
Tue 16/08/13 |
Fri 14/02/14 |
ASIC
Development |
85 days |
Mon 20/01/14 |
Fri 16/05/14 |
Viper
Miner Board Design |
95 days |
Mon 13/01/14 |
Fri 23/05/14 |
Viper
Miner Firmware Development & Testing |
118 days |
Wed 01/01/14 |
Fri 13/06/14 |
Mechanical,
Thermal & Misc |
69 days |
Mon 13/01/14 |
Thu 17/04/14 |
System
Assembly & Testing |
2 days |
Mon 16/06/14 |
Tue 17/06/14 |
System
Integration & Testing |
20 days |
Wed 18/06/14 |
Tue 15/07/14 |
User
Manual |
12 days |
Fri 18/04/14 |
Mon 05/05/14 |
Roadmap (recap):